May to December 2009

Starting the project:

- To form the basement area of over 1-ha, 80,000 cubic metres were excavated, involving 10,000 truckloads of material being removed from the site

- Basement construction was through Belfast "sleech": a notoriously difficult mixture of sand, gravel and boulder clay, beside the River Lagan, at 8m below sea level

- Over 1,000 secant piles covering a perimeter of approx 500 metres were used. Piles 600mm diameter to a depth of 18m were restrained by ground anchors

- Over 1,000 bearing piles were used, 600mm diameter to a depth of 23m

- Basement concrete slab was 1.1m deep and used over 2,500 tons of reinforcement steel

- The first concrete pour covered almost 0.5-ha to a volume of 4,200m3.

- It was the largest ever concrete pour on the island of Ireland: over 700 concrete truck deliveries; a truck load every 2 minutes for 24 hours, requiring eight concrete pumps

- In total, over 10,000 m3 of low carbon concrete was used in the basement construction contributing to a CO2 saving of 1,296 tonnes. The same emissions saving would require taking 416 cars off the road for a year, or saving 408.3 years' electricity in the average home
 

Nov-2009

Back to top


  • Titanic Belfast ®
    is owned by:
  • Titanic Foundation Limited
  • Funded in
    partnership by:
  • Northern Ireland Tourist Board
  • Belfast City Council
  • Belfast Harbour Commissioners
  • Titanic Quarter
  • Designed
    & built by:
  • Harcourt Developments
  • Key Supporting Partner:
  • Danske Bank
  • Supported By:
  • Value Cabs
  • Diageo